Initial start-up Operation
© 2008 19
3
Preparations for initial commissioning
(Maintenance schedule E 10)
z
Remove engine corrosion protection
z
Remove any transport devices.
z
Check the battery and cable connections and
mount if necessary.
z
Check belt tension (
43).
z
Have the engine monitor or warning system
checked by authorised personnel.
z
Check the engine mounting.
z
Check that all hose unions and clips fit properly.
The following additional work must be carried
out on generally overhauled engines:
z
Check the fuel pre-filter and main filter and
change if necessary.
z
Check the intake air cleaner (if available, main-
tain according to maintenance indicator).
z
Drain lubricating oil and condensation water from
the charge air cooler.
z
Fill with engine lube oil.
Fill with engine lube oil
z
Fill the engine with lubricating oil via the lubricat-
Low lubricating oil level and overfilling lead
to engine damage.
The engines are generally supplied without
lubricating oil filling.
Select lubricating oil quality and viscosity
before filling.
Order DEUTZ lubricating oils from your
DEUTZ partner
ing oil filler neck.
z
Observe the lubricating oil filling level (
58).
Pour in fuel
z
The fuel low pressure system must be vented be-
fore the first start-up after filling with the manualy
supply pump.
Only use clean commercially available brand diesel
fuel. Observe fuel quality (
28).
Use summer or winter-grade fuel, depending on the
ambient temperature.
Only re-fuel when the engine is not running.
Ensure cleanliness.
Do not spill fuel.
Additional venting of the fuel system by a 5
minute trial run at idle speed or on low load
is absolutely essential.